Estonia: Repairs on EstLink 2 power cable to last until August 2024

Estonia’s electricity transmission system operator, Elering, has finally located the fault in the EstLink 2 power cable connecting Estonia and Finland, ERR reports. Complexities due to the area’s terrain and the cable’s design mean that repairs will now extend until the end of August 2024, the company announced. Initially, Elering expected the cable to be…

Read More